Installationsanleitung Box Verbausysteme (ontgraven)

1. Pre-excavate approx. 1.5 m depending on the stability of the soil.

2. The Box-element is lowered into the pre-excavated trench.

3. Excavation is continued. A maximum of 0.5 m is advised, depending on the stability of the soil.

4. Both sides of the Box are pushed independently.

5. When both side are lowered, excavation will continue.

6. Excavation is continued. A maximum of 0.5 m is advised, depending on the stability of the soil.

7. Both side of the Box are pushed independently.

8. After reaching full depth, pipes can be layed.